Heinen & Hopman HVAC equipment installation and adjustment supervision at Wellhead Platofrom of Yu. Korchagin oilfield
Category | Completed |
Construction facility | 2nd phase of Yu. Korchagin oilfield wellhead platform |
General customer | OOO “Lukoil Nizhnevolzhskneft” |
Start | May 2018 |
Finish | July 2018 |
The bulk of the work:
HVAC systems installation and adjustment supervision:
- Equipment preparation for individual testing of HVAC system
- Corrective actions as per requirements of the Customer and HVAС equipment Vendor
- HVAC system equipment testing