| Category | Completed |
| Construction facility | 1st phase of V. Filanovsky oilfield |
| General customer | “Lukoil Nizhnevolzhskneft” OOO |
| Start | 2015 November |
| Finish | 2017 April |
The bulk of the work:
- Exhaust heat boilers of 50 MW capacity assembly and installation
- Outfitting work
- Corrective actions related to civil and installation work
- Preparation for IRP-1 systems commissioning under Customer’s Supervision
The main objective is to prepare functional units for commissioning.