1st phase of V.Filanovsky oilfield IRP-1

Category Completed
Construction facility 1st phase of V. Filanovsky oilfield IRP-1 (Ice Resistant Platform)
General customer “Lukoil Nizhnevolzhskneft” OOO
Start 2015 November
Finish 2017 April

The bulk of the work:

  • Exhaust heat boilers of 50 MW capacity assembly and installation
  • Outfitting work
  • Corrective actions related to civil and installation work
  • Preparation for IRP-1 systems commissioning under Customer’s Supervision

The main objective is to prepare functional units for commissioning.