Living Quarters Platform (LQM-2) commissioning
Category | Completed |
Construction facility | 2nd phase of V. Filanovsky field |
General customer | “Lukoil Nizhnevolzhskneft” OOO |
Start | 2017 March |
Finish | 2017 September |
Review of construction readiness and system readiness for individual testing.
Equipment individual testing.
LQM-2 (Living Quarters Platform) shipboard and energy facility commissioning:
Shipboard equipment facilities:
- Drain port system;
- Water based fire system
- Foam fire system
- Fire sprinkler system
- Gaseous fire suppression
- Smoke ventilation system
- Utility fresh water system
- Process fresh water system
- Seawater supply system
- Deck drain system
- Oily waters collecting and discharge system
- Steam supply system for ice removal
- Heating system
- Desalination system
- Nitrogen and pressed air system
- Chemical ventilation system
- Water sprinkling system
POWER COMPLEX
- Emergency diesel generator and its supporting systems
- Diesel fuel acceptance, pumping and separation system